Plastic construction

Aug 14, 2024

Leave a message

(1) Installation and fixation of anchoring devices. Anchor devices should be installed on the furnace wall and roof according to the design specifications before construction.
The furnace wall anchoring device is generally composed of special-shaped refractory bricks and metal parts welded to the furnace shell.
The anchor bricks for the furnace wall should be fixed at the level where the plastic can be pounded to its bottom surface, and the bolts connected to the metal parts should be tightened.
The roof anchoring device is composed of special-shaped refractory bricks and metal pendants. After they are connected, they are hung on steel beams.
The installation of roof anchor bricks should be carried out after the plastic is laid and compacted to the corresponding position. Before installation, first drive the wooden mold bricks into the compacted plastic body to form a concave convex surface that is the same as the brick surface, and then embed and fix the anchor bricks. At this point, attention should also be paid to the tight fit between the anchor brick and the plastic body.
(2) Laying and pounding of plastic. The laying of plastic blanks should be staggered and tightly packed, and should be compacted layer by layer, that is, the second layer can only be laid after the first layer of blanks has been compacted completely. The direction of compaction should be perpendicular to the construction surface. When using bulk plastic, the thickness of each layer of material should not exceed 100mm.
When using a pneumatic compactor for compaction, the operator should tightly grip the hammer body and move forward in a way where the hammer heads overlap by 2/3 and the rows overlap by 1/2, and repeat the compaction 3-4 times. In case of construction gaps, plastic film cloth should be used to cover the compacted material.
When the pounding is interrupted for a long time, the joint should be left at the centerline of the anchor bricks in the same row. When continuing to pound, the surface should be scraped.
The thickness of the compacted furnace wall is generally slightly larger than the design size (6-8mm larger when the formwork is supported; about 20mm larger when the formwork is not supported), in order to facilitate finishing after construction. When repairing, use cutting tools to cut off excess parts on the surface according to the design dimensions, so that the internal pores are exposed.
Plastic expansion joints should be left according to design specifications. The expansion joint of the furnace wall is left as a longitudinal straight joint, with a 2mm thick polyvinyl chloride corrugated board sandwiched inside the joint. Both sides of the waveform board should be uniformly pounded at the same time to form a straight expansion joint. When leaving expansion joints at corners, a wooden template can be fixed at the expansion joint position, and then pounded from two different directions of the furnace wall at the same time. After completion, the wooden board can be removed and filled with refractory fibers inside the joint.
The plastic pounding on the furnace top can generally be carried out in sections simultaneously. The sloping roof should start from the lower turning point (construction joint). During tamping, the operator holds the tamping machine in a horizontal direction. Due to the lack of self weight impact force of the hammer, it appears laborious. Therefore, during construction, special attention should be paid to evenly pounding to ensure a tight bond between the materials. Generally, a funnel-shaped gap is left at the top of the furnace when the door is closed, and then carefully pounded.